March 10, 2016
Construction of new Chimpex Grain Terminal well under way
The mild winter in Romania has enabled the construction work in Constanta to move on at full speed and the erection of the first two cells has started. We are confident that the very ambitious deadline for Phase One of the project will be achieved and by September 2016, we should have 10 cells ready for operation. The project is scheduled to be finalized by June 2017.